Page 1585 - RERA Performance Report 2020
P. 1585

Project Name : RIDDHI RESIDENCY (UPRERAPRJ17614)


         District                              Gorakhpur

         Promoter Name                         HARI BANSH SHUKLA
         Project Category                      Residential

         Sanctioning Competent                 Gorakhpur Development Authorit
         Authority
         Start Date                            25-09-2018

         Original Completion Date              26-09-2021
         Revised Completion Date               25-03-2022
         Validity of Sanction Plan             27-05-2023

         Total Towers / Blocks
         Total Units

         Completed Towers / Blocks
         Completed Units

         Last Quarterly Progress               Oct - Dec 2018
         Report
         Penalty For Not Filing QPR            100000

         Overall Physical Progress (%)
         Overall Financial Progress
         (%)

         Date of Completion                    Work In Progress
         Certificate
         Date of Occupancy Certificate Work In Progress

         Complaints by the Allottees           0
         Orders (Refund + Possession) Refund- 0, Possession- 0

         Click below for more details:
         1. Project Registration Details
         Disclaimer:

         The information relating to the projects, given in this report, has been taken from the
         details provided by the promoter in the application for registration and subsequent
         updates by the promoter on the website of U.P. RERA.
             The information has also been taken from the details submitted by the promoter
         through the online form provided by the Authority for the purposes of updating the
         important details relating to the project in this report.
             The Authority has not verified all the information relating to the projects in this
         report.
   1580   1581   1582   1583   1584   1585   1586   1587   1588   1589   1590