Project Name : GOVIND COMPLEX (UPRERAPRJ10892)


         District                              Gorakhpur

         Promoter Name                         P KE PRIME ESTATES
         Project Category                      Commercial

         Sanctioning Competent                 Gorakhpur Development Authorit
         Authority
         Start Date                            03-06-2017

         Original Completion Date              03-06-2020
         Revised Completion Date               02-12-2020
         Validity of Sanction Plan             03-06-2022

         Total Towers / Blocks
         Total Units

         Completed Towers / Blocks
         Completed Units

         Last Quarterly Progress
         Report
         Penalty For Not Filing QPR            200000

         Overall Physical Progress (%)
         Overall Financial Progress
         (%)

         Date of Completion                    Status Not Available
         Certificate
         Date of Occupancy Certificate Status Not Available

         Complaints by the Allottees           0
         Orders (Refund + Possession) Refund- 0, Possession- 0

         Click below for more details:
         1. Project Registration Details
         Disclaimer:

         The information relating to the projects, given in this report, has been taken from the
         details provided by the promoter in the application for registration and subsequent
         updates by the promoter on the website of U.P. RERA.
             The information has also been taken from the details submitted by the promoter
         through the online form provided by the Authority for the purposes of updating the
         important details relating to the project in this report.
             The Authority has not verified all the information relating to the projects in this
         report.
   1585   1586   1587   1588   1589   1590   1591   1592   1593   1594   1595