Page 1583 - RERA Performance Report 2020
P. 1583
Project Name : VASUNDHARA ENCLAVE ( PHASE-II )
(UPRERAPRJ12563)
District Gorakhpur
Promoter Name Gorakhpur Development Authority
Project Category Residential
Sanctioning Competent Gorakhpur Development Authorit
Authority
Start Date 17-08-2015
Original Completion Date 16-08-2017
Revised Completion Date
Validity of Sanction Plan 21-01-2020
Total Towers / Blocks 20
Total Units 240
Completed Towers / Blocks 20
Completed Units 240
Last Quarterly Progress
Report
Penalty For Not Filing QPR None
Overall Physical Progress (%) 100
Overall Financial Progress 90
(%)
Date of Completion 01-10-2017
Certificate
Date of Occupancy Certificate
Complaints by the Allottees 23
Orders (Refund + Possession) Refund- 0, Possession- 0
Click below for more details:
1. Project Registration Details
2.Additional Details Submitted by Promoter
Disclaimer:
The information relating to the projects, given in this report, has been taken from the
details provided by the promoter in the application for registration and subsequent
updates by the promoter on the website of U.P. RERA.
The information has also been taken from the details submitted by the promoter
through the online form provided by the Authority for the purposes of updating the
important details relating to the project in this report.
The Authority has not verified all the information relating to the projects in this
report.