Project Name : THE ROMANO (PHASE-II) (UPRERAPRJ5705)


         District                              Gautam Buddha Nagar

                                               IVR PRIME DEVELOPERS (AVADI) PRIVATE
         Promoter Name
                                               LIMITED
         Project Category                      Residential

         Sanctioning Competent                 Noida Authority
         Authority
         Start Date                            22-02-2014

         Original Completion Date              30-12-2019
         Revised Completion Date

         Validity of Sanction Plan             14-02-2024
         Total Towers / Blocks                 10

         Total Units                           1210
         Completed Towers / Blocks             10
         Completed Units                       0

         Last Quarterly Progress               Jan - Mar 2020
         Report

         Penalty For Not Filing QPR            None
         Overall Physical Progress (%) 50
         Overall Financial Progress            50
         (%)

         Date of Completion                    Status Not Available
         Certificate

         Date of Occupancy Certificate Status Not Available
         Complaints by the Allottees           33
         Orders (Refund + Possession) Refund- 1, Possession- 13

         Click below for more details:
         1. Project Registration Details
         2.Additional Details Submitted by Promoter

         Disclaimer:
         The information relating to the projects, given in this report, has been taken from the
         details provided by the promoter in the application for registration and subsequent
         updates by the promoter on the website of U.P. RERA.
             The information has also been taken from the details submitted by the promoter
         through the online form provided by the Authority for the purposes of updating the
         important details relating to the project in this report.

             The Authority has not verified all the information relating to the projects in this
         report.
   789   790   791   792   793   794   795   796   797   798   799