Page 789 - RERA Performance Report 2020
P. 789

Project Name : AMBROSIA (PHASE-1: TOWER A B C D & E)
         (UPRERAPRJ5814)

         District                              Gautam Buddha Nagar

                                               IVR PRIME DEVELOPERS (AVADI) PRIVATE
         Promoter Name
                                               LIMITED
         Project Category                      Residential

         Sanctioning Competent                 Noida Authority
         Authority
         Start Date                            06-12-2013

         Original Completion Date              31-12-2019
         Revised Completion Date               29-06-2021

         Validity of Sanction Plan             15-02-2024
         Total Towers / Blocks                 5

         Total Units                           854
         Completed Towers / Blocks             0
         Completed Units                       0

         Last Quarterly Progress               Apr - Jun 2020
         Report

         Penalty For Not Filing QPR            None
         Overall Physical Progress (%) 60
         Overall Financial Progress            57
         (%)

         Date of Completion                    Work In Progress
         Certificate

         Date of Occupancy Certificate Work In Progress
         Complaints by the Allottees           26
         Orders (Refund + Possession) Refund- 2, Possession- 11

         Click below for more details:
         1. Project Registration Details
         2.Additional Details Submitted by Promoter

         Disclaimer:
         The information relating to the projects, given in this report, has been taken from the
         details provided by the promoter in the application for registration and subsequent
         updates by the promoter on the website of U.P. RERA.
             The information has also been taken from the details submitted by the promoter
         through the online form provided by the Authority for the purposes of updating the
         important details relating to the project in this report.

             The Authority has not verified all the information relating to the projects in this
         report.