Project Name : ANTRIKSH VALLEY (UPRERAPRJ5929)


         District                              Gautam Buddha Nagar

                                               DILIGENT BUILDERS PVT. LTD. (ANTRIKSH
         Promoter Name
                                               GROUP)
         Project Category                      Residential

         Sanctioning Competent                 Greater Noida Authority
         Authority
         Start Date                            23-05-2014

         Original Completion Date              23-05-2022
         Revised Completion Date               25-01-2022

         Validity of Sanction Plan             24-05-2014
         Total Towers / Blocks                 2

         Total Units                           360
         Completed Towers / Blocks             0
         Completed Units                       153

         Last Quarterly Progress
         Report

         Penalty For Not Filing QPR            100000
         Overall Physical Progress (%) 40
         Overall Financial Progress            32
         (%)

         Date of Completion                    Work In Progress
         Certificate

         Date of Occupancy Certificate Work In Progress
         Complaints by the Allottees           18
         Orders (Refund + Possession) Refund- 4, Possession- 2

         Click below for more details:
         1. Project Registration Details
         2.Additional Details Submitted by Promoter

         Disclaimer:
         The information relating to the projects, given in this report, has been taken from the
         details provided by the promoter in the application for registration and subsequent
         updates by the promoter on the website of U.P. RERA.
             The information has also been taken from the details submitted by the promoter
         through the online form provided by the Authority for the purposes of updating the
         important details relating to the project in this report.

             The Authority has not verified all the information relating to the projects in this
         report.
   638   639   640   641   642   643   644   645   646   647   648