Project Name : DEVIKA GOLD HOMZ (UPRERAPRJ5398)


         District                              Gautam Buddha Nagar

         Promoter Name                         DEVIKA GOLD HOMZ PVT. LTD.
         Project Category                      Residential

         Sanctioning Competent                 Greater Noida Authority
         Authority
         Start Date                            07-12-2010

         Original Completion Date              31-12-2019
         Revised Completion Date               29-12-2020
         Validity of Sanction Plan             31-12-2020

         Total Towers / Blocks                 6
         Total Units                           723

         Completed Towers / Blocks             0
         Completed Units                       723

         Last Quarterly Progress               Oct - Dec 2019
         Report
         Penalty For Not Filing QPR            200000

         Overall Physical Progress (%) 96
         Overall Financial Progress            95
         (%)

         Date of Completion                    Work In Progress
         Certificate
         Date of Occupancy Certificate Work In Progress

         Complaints by the Allottees           56
         Orders (Refund + Possession) Refund- 0, Possession- 32

         Click below for more details:
         1. Project Registration Details
         2.Additional Details Submitted by Promoter

         Disclaimer:
         The information relating to the projects, given in this report, has been taken from the
         details provided by the promoter in the application for registration and subsequent
         updates by the promoter on the website of U.P. RERA.
             The information has also been taken from the details submitted by the promoter
         through the online form provided by the Authority for the purposes of updating the
         important details relating to the project in this report.
             The Authority has not verified all the information relating to the projects in this

         report.
   634   635   636   637   638   639   640   641   642   643   644