Page 265 - RERA Performance Report 2020
P. 265

Project Name : NAVYUG TOWER-15 (PHASE-3)
         (UPRERAPRJ17474)

         District                              Allahabaad

         Promoter Name                         New Modern Buildwell Private Limited
         Project Category                      Residential

         Sanctioning Competent                 Allahabad Development Authorit
         Authority
         Start Date                            01-09-2018

         Original Completion Date              30-08-2023
         Revised Completion Date               29-02-2024
         Validity of Sanction Plan             29-02-2024

         Total Towers / Blocks                 1
         Total Units                           104

         Completed Towers / Blocks             0
         Completed Units                       0

         Last Quarterly Progress               Apr - Jun 2020
         Report
         Penalty For Not Filing QPR            100000

         Overall Physical Progress (%) 9
         Overall Financial Progress            9
         (%)

         Date of Completion                    Work In Progress
         Certificate
         Date of Occupancy Certificate Work In Progress

         Complaints by the Allottees           0
         Orders (Refund + Possession) Refund- 0, Possession- 0

         Click below for more details:
         1. Project Registration Details
         2.Additional Details Submitted by Promoter

         Disclaimer:
         The information relating to the projects, given in this report, has been taken from the
         details provided by the promoter in the application for registration and subsequent
         updates by the promoter on the website of U.P. RERA.
             The information has also been taken from the details submitted by the promoter
         through the online form provided by the Authority for the purposes of updating the
         important details relating to the project in this report.
             The Authority has not verified all the information relating to the projects in this

         report.