Project Name : NAVYUG PHASE-4 (NIRJHAR)
         (UPRERAPRJ739367)

         District                              Allahabaad

         Promoter Name                         New Modern Buildwell Private Limited
         Project Category                      Residential

         Sanctioning Competent                 Allahabad Development Authorit
         Authority
         Start Date                            10-04-2019

         Original Completion Date              09-04-2021
         Revised Completion Date               08-10-2021
         Validity of Sanction Plan             05-10-2024

         Total Towers / Blocks                 1
         Total Units                           125

         Completed Towers / Blocks             0
         Completed Units                       0

         Last Quarterly Progress               Apr - Jun 2020
         Report
         Penalty For Not Filing QPR            None

         Overall Physical Progress (%) 29
         Overall Financial Progress            38
         (%)

         Date of Completion                    Work In Progress
         Certificate
         Date of Occupancy Certificate Work In Progress

         Complaints by the Allottees           0
         Orders (Refund + Possession) Refund- 0, Possession- 0

         Click below for more details:
         1. Project Registration Details
         2.Additional Details Submitted by Promoter

         Disclaimer:
         The information relating to the projects, given in this report, has been taken from the
         details provided by the promoter in the application for registration and subsequent
         updates by the promoter on the website of U.P. RERA.
             The information has also been taken from the details submitted by the promoter
         through the online form provided by the Authority for the purposes of updating the
         important details relating to the project in this report.
             The Authority has not verified all the information relating to the projects in this

         report.
   258   259   260   261   262   263   264   265   266   267   268