Page 2646 - RERA Performance Report 2020
P. 2646

Project Name : PRADHAN MANTRI AWASYOJANA
         (SHAHARI) (UPRERAPRJ17456)

         District                              Unnao

                                               UNNAO-SHUKLAGANJ DEVELOPMENT
         Promoter Name
                                               AUTHORITY
         Project Category                      Residential

         Sanctioning Competent                 Unnao Shuklaganj Development A
         Authority
         Start Date                            15-10-2018

         Original Completion Date              14-10-2020
         Revised Completion Date               13-04-2021

         Validity of Sanction Plan             24-08-2023
         Total Towers / Blocks                 1

         Total Units                           720
         Completed Towers / Blocks             0
         Completed Units                       0

         Last Quarterly Progress               Jul - Sep 2018
         Report

         Penalty For Not Filing QPR            100000
         Overall Physical Progress (%) 55
         Overall Financial Progress            38
         (%)

         Date of Completion                    Work In Progress
         Certificate

         Date of Occupancy Certificate Work In Progress
         Complaints by the Allottees           0
         Orders (Refund + Possession) Refund- 0, Possession- 0

         Click below for more details:
         1. Project Registration Details
         2.Additional Details Submitted by Promoter

         Disclaimer:
         The information relating to the projects, given in this report, has been taken from the
         details provided by the promoter in the application for registration and subsequent
         updates by the promoter on the website of U.P. RERA.
             The information has also been taken from the details submitted by the promoter
         through the online form provided by the Authority for the purposes of updating the
         important details relating to the project in this report.

             The Authority has not verified all the information relating to the projects in this
         report.
   2641   2642   2643   2644   2645   2646   2647   2648   2649   2650   2651