Page 2643 - RERA Performance Report 2020
P. 2643
Project Name : PMAY EWS 192 NO. FLATS LOHRAMAU
YOJNA (UPRERAPRJ15327)
District Sultanpur
Promoter Name U.P. Awas Evam Vikas Parishad
Project Category Residential
Sanctioning Competent U.P. Awas Evam Vikas Parishad
Authority
Start Date 26-02-2018
Original Completion Date 25-12-2019
Revised Completion Date 23-06-2021
Validity of Sanction Plan 30-09-2021
Total Towers / Blocks 1
Total Units 192
Completed Towers / Blocks 0
Completed Units 24
Last Quarterly Progress Apr - Jun 2020
Report
Penalty For Not Filing QPR None
Overall Physical Progress (%) 70
Overall Financial Progress 60
(%)
Date of Completion Work In Progress
Certificate
Date of Occupancy Certificate Work In Progress
Complaints by the Allottees 0
Orders (Refund + Possession) Refund- 0, Possession- 0
Click below for more details:
1. Project Registration Details
2.Additional Details Submitted by Promoter
Disclaimer:
The information relating to the projects, given in this report, has been taken from the
details provided by the promoter in the application for registration and subsequent
updates by the promoter on the website of U.P. RERA.
The information has also been taken from the details submitted by the promoter
through the online form provided by the Authority for the purposes of updating the
important details relating to the project in this report.
The Authority has not verified all the information relating to the projects in this
report.