Project Name : RAJENDRA CENTRE (UPRERAPRJ13798)


         District                              Agra

         Promoter Name                         RAJENDRA DEVELOPERS
         Project Category                      Commercial

         Sanctioning Competent                 U.P. Awas Evam Vikas Parishad
         Authority
         Start Date                            01-02-2014

         Original Completion Date              31-12-2017
         Revised Completion Date
         Validity of Sanction Plan             17-02-2015

         Total Towers / Blocks
         Total Units

         Completed Towers / Blocks
         Completed Units

         Last Quarterly Progress
         Report
         Penalty For Not Filing QPR            None

         Overall Physical Progress (%)
         Overall Financial Progress
         (%)

         Date of Completion                    Status Not Available
         Certificate
         Date of Occupancy Certificate Status Not Available

         Complaints by the Allottees           0
         Orders (Refund + Possession) Refund- 0, Possession- 0

         Click below for more details:
         1. Project Registration Details
         Disclaimer:

         The information relating to the projects, given in this report, has been taken from the
         details provided by the promoter in the application for registration and subsequent
         updates by the promoter on the website of U.P. RERA.
             The information has also been taken from the details submitted by the promoter
         through the online form provided by the Authority for the purposes of updating the
         important details relating to the project in this report.
             The Authority has not verified all the information relating to the projects in this
         report.
   165   166   167   168   169   170   171   172   173   174   175