Page 165 - RERA Performance Report 2020
P. 165

Project Name : PUSHPANJALI SEASONS PHASE-1
         (UPRERAPRJ13009)

         District                              Agra

         Promoter Name                         Pushpanjali Constructions Private Limited
         Project Category                      Residential

         Sanctioning Competent                 Agra Development Authority
         Authority
         Start Date                            01-07-2011

         Original Completion Date              30-09-2021
         Revised Completion Date               18-02-2020
         Validity of Sanction Plan             08-05-2022

         Total Towers / Blocks                 7
         Total Units                           668

         Completed Towers / Blocks             0
         Completed Units                       420

         Last Quarterly Progress
         Report
         Penalty For Not Filing QPR            200000

         Overall Physical Progress (%) 58
         Overall Financial Progress            58
         (%)

         Date of Completion                    Status Not Available
         Certificate
         Date of Occupancy Certificate Status Not Available

         Complaints by the Allottees           0
         Orders (Refund + Possession) Refund- 0, Possession- 0

         Click below for more details:
         1. Project Registration Details
         2.Additional Details Submitted by Promoter

         Disclaimer:
         The information relating to the projects, given in this report, has been taken from the
         details provided by the promoter in the application for registration and subsequent
         updates by the promoter on the website of U.P. RERA.
             The information has also been taken from the details submitted by the promoter
         through the online form provided by the Authority for the purposes of updating the
         important details relating to the project in this report.
             The Authority has not verified all the information relating to the projects in this

         report.