Page 1429 - RERA Performance Report 2020
P. 1429
Project Name : MAGNUM OASIS GREEN (UPRERAPRJ6761)
District Ghaziabad
Promoter Name RMS BUILDERS PRIVATE LIMITED
Project Category Residential
Sanctioning Competent UP STATE INDUSTRIAL DEVELOPEME
Authority
Start Date 27-08-2015
Original Completion Date 26-08-2020
Revised Completion Date 25-02-2021
Validity of Sanction Plan 22-05-2021
Total Towers / Blocks 3
Total Units 402
Completed Towers / Blocks 0
Completed Units 168
Last Quarterly Progress Apr - Jun 2018
Report
Penalty For Not Filing QPR 100000
Overall Physical Progress (%) 40
Overall Financial Progress 32
(%)
Date of Completion Work In Progress
Certificate
Date of Occupancy Certificate Work In Progress
Complaints by the Allottees 2
Orders (Refund + Possession) Refund- 0, Possession- 0
Click below for more details:
1. Project Registration Details
2.Additional Details Submitted by Promoter
Disclaimer:
The information relating to the projects, given in this report, has been taken from the
details provided by the promoter in the application for registration and subsequent
updates by the promoter on the website of U.P. RERA.
The information has also been taken from the details submitted by the promoter
through the online form provided by the Authority for the purposes of updating the
important details relating to the project in this report.
The Authority has not verified all the information relating to the projects in this
report.