Page 1428 - RERA Performance Report 2020
P. 1428

Project Name : HINDON GREEN VALLEY (UPRERAPRJ3203)


         District                              Ghaziabad

         Promoter Name                         Rishabh Buildwell Pvt. Ltd.
         Project Category                      Residential

         Sanctioning Competent                 Ghaziabad Development Authorit
         Authority
         Start Date                            07-05-2017

         Original Completion Date              30-06-2022
         Revised Completion Date               29-12-2022
         Validity of Sanction Plan             17-06-2021

         Total Towers / Blocks                 4
         Total Units                           786

         Completed Towers / Blocks             0
         Completed Units                       0

         Last Quarterly Progress               Apr - Jun 2020
         Report
         Penalty For Not Filing QPR            None

         Overall Physical Progress (%) 26
         Overall Financial Progress            52
         (%)

         Date of Completion                    Work In Progress
         Certificate
         Date of Occupancy Certificate Work In Progress

         Complaints by the Allottees           2
         Orders (Refund + Possession) Refund- 0, Possession- 0

         Click below for more details:
         1. Project Registration Details
         2.Additional Details Submitted by Promoter

         Disclaimer:
         The information relating to the projects, given in this report, has been taken from the
         details provided by the promoter in the application for registration and subsequent
         updates by the promoter on the website of U.P. RERA.
             The information has also been taken from the details submitted by the promoter
         through the online form provided by the Authority for the purposes of updating the
         important details relating to the project in this report.
             The Authority has not verified all the information relating to the projects in this

         report.
   1423   1424   1425   1426   1427   1428   1429   1430   1431   1432   1433