Page 134 - RERA Performance Report 2020
P. 134

Project Name : KAILASH RESIDENCY PART 1
         (UPRERAPRJ9644)

         District                              Agra

         Promoter Name                         Maa Sarswati Infradevelopers Private Limited
         Project Category                      Residential

         Sanctioning Competent                 Agra Development Authority
         Authority
         Start Date                            01-10-2014

         Original Completion Date              31-12-2020
         Revised Completion Date               30-06-2021
         Validity of Sanction Plan             06-06-2011

         Total Towers / Blocks                 1
         Total Units                           53

         Completed Towers / Blocks             0
         Completed Units                       0

         Last Quarterly Progress               Apr - Jun 2020
         Report
         Penalty For Not Filing QPR            None

         Overall Physical Progress (%) 73
         Overall Financial Progress            88
         (%)

         Date of Completion                    Work In Progress
         Certificate
         Date of Occupancy Certificate Work In Progress

         Complaints by the Allottees           0
         Orders (Refund + Possession) Refund- 0, Possession- 0

         Click below for more details:
         1. Project Registration Details
         2.Additional Details Submitted by Promoter

         Disclaimer:
         The information relating to the projects, given in this report, has been taken from the
         details provided by the promoter in the application for registration and subsequent
         updates by the promoter on the website of U.P. RERA.
             The information has also been taken from the details submitted by the promoter
         through the online form provided by the Authority for the purposes of updating the
         important details relating to the project in this report.
             The Authority has not verified all the information relating to the projects in this

         report.
   129   130   131   132   133   134   135   136   137   138   139