Page 130 - RERA Performance Report 2020
P. 130

Project Name : SINGHAL DREAM CITY (UPRERAPRJ6746)


         District                              Agra

         Promoter Name                         M R INFRAESTATE PRIVATE LIMITED
         Project Category                      Residential

         Sanctioning Competent                 Agra Development Authority
         Authority
         Start Date                            03-05-2017

         Original Completion Date              30-06-2021
         Revised Completion Date               29-12-2021
         Validity of Sanction Plan             04-08-2021

         Total Towers / Blocks                 7
         Total Units                           540

         Completed Towers / Blocks             1
         Completed Units                       212

         Last Quarterly Progress               Apr - Jun 2020
         Report
         Penalty For Not Filing QPR            200000

         Overall Physical Progress (%) 60
         Overall Financial Progress            75
         (%)

         Date of Completion                    Work In Progress
         Certificate
         Date of Occupancy Certificate Work In Progress

         Complaints by the Allottees           1
         Orders (Refund + Possession) Refund- 1, Possession- 0

         Click below for more details:
         1. Project Registration Details
         2.Additional Details Submitted by Promoter

         Disclaimer:
         The information relating to the projects, given in this report, has been taken from the
         details provided by the promoter in the application for registration and subsequent
         updates by the promoter on the website of U.P. RERA.
             The information has also been taken from the details submitted by the promoter
         through the online form provided by the Authority for the purposes of updating the
         important details relating to the project in this report.
             The Authority has not verified all the information relating to the projects in this

         report.
   125   126   127   128   129   130   131   132   133   134   135