Project Name : RPS01,RRPS01 AND RRPS02 (SECTOR 18 AND
         20) ,YEIDA (UPRERAPRJ282078)

         District                              Gautam Buddha Nagar

         Promoter Name                         Yamuna Expressway Industrial devlopment Authority
         Project Category                      Residential

         Sanctioning Competent                 Yamuna Expressway Authority
         Authority
         Start Date                            11-12-2013

         Original Completion Date              09-01-2024
         Revised Completion Date               08-07-2024
         Validity of Sanction Plan             08-07-2024

         Total Towers / Blocks                 5
         Total Units                           23662

         Completed Towers / Blocks             0
         Completed Units                       8736

         Last Quarterly Progress               Apr - Jun 2020
         Report
         Penalty For Not Filing QPR            None

         Overall Physical Progress (%) 59
         Overall Financial Progress            59
         (%)

         Date of Completion                    Work In Progress
         Certificate
         Date of Occupancy Certificate Work In Progress

         Complaints by the Allottees           4
         Orders (Refund + Possession) Refund- 0, Possession- 0

         Click below for more details:
         1. Project Registration Details
         2.Additional Details Submitted by Promoter

         Disclaimer:
         The information relating to the projects, given in this report, has been taken from the
         details provided by the promoter in the application for registration and subsequent
         updates by the promoter on the website of U.P. RERA.
             The information has also been taken from the details submitted by the promoter
         through the online form provided by the Authority for the purposes of updating the
         important details relating to the project in this report.
             The Authority has not verified all the information relating to the projects in this

         report.
   1204   1205   1206   1207   1208   1209   1210   1211   1212   1213   1214