Project Name : GH06, SEC-22D, YEIDA (UPRERAPRJ8947)
District Gautam Buddha Nagar
Promoter Name Yamuna Expressway Industrial devlopment Authority
Project Category Residential
Sanctioning Competent Yamuna Expressway Authority
Authority
Start Date 10-02-2014
Original Completion Date 30-12-2019
Revised Completion Date
Validity of Sanction Plan 02-10-2021
Total Towers / Blocks 2
Total Units 256
Completed Towers / Blocks 2
Completed Units 256
Last Quarterly Progress Oct - Dec 2019
Report
Penalty For Not Filing QPR None
Overall Physical Progress (%) 90
Overall Financial Progress 90
(%)
Date of Completion Status Not Available
Certificate
Date of Occupancy Certificate Status Not Available
Complaints by the Allottees 1
Orders (Refund + Possession) Refund- 0, Possession- 1
Click below for more details:
1. Project Registration Details
2.Additional Details Submitted by Promoter
Disclaimer:
The information relating to the projects, given in this report, has been taken from the
details provided by the promoter in the application for registration and subsequent
updates by the promoter on the website of U.P. RERA.
The information has also been taken from the details submitted by the promoter
through the online form provided by the Authority for the purposes of updating the
important details relating to the project in this report.
The Authority has not verified all the information relating to the projects in this
report.