Project Name : SUPERTECH ECO VILLAGE-3 PHASE-3
         (UPRERAPRJ8319)

         District                              Gautam Buddha Nagar

         Promoter Name                         SUPERTECH LIMITED
         Project Category                      Residential

         Sanctioning Competent                 Greater Noida Authority
         Authority
         Start Date                            31-12-2012

         Original Completion Date              31-05-2021
         Revised Completion Date               30-11-2021
         Validity of Sanction Plan             08-04-2019

         Total Towers / Blocks                 1
         Total Units                           234

         Completed Towers / Blocks             0
         Completed Units                       0

         Last Quarterly Progress               Apr - Jun 2020
         Report
         Penalty For Not Filing QPR            None

         Overall Physical Progress (%) 12
         Overall Financial Progress            12
         (%)

         Date of Completion                    Work In Progress
         Certificate
         Date of Occupancy Certificate Work In Progress

         Complaints by the Allottees           23
         Orders (Refund + Possession) Refund- 1, Possession- 8

         Click below for more details:
         1. Project Registration Details
         2.Additional Details Submitted by Promoter

         Disclaimer:
         The information relating to the projects, given in this report, has been taken from the
         details provided by the promoter in the application for registration and subsequent
         updates by the promoter on the website of U.P. RERA.
             The information has also been taken from the details submitted by the promoter
         through the online form provided by the Authority for the purposes of updating the
         important details relating to the project in this report.
             The Authority has not verified all the information relating to the projects in this

         report.
   1106   1107   1108   1109   1110   1111   1112   1113   1114   1115   1116