Page 1110 - RERA Performance Report 2020
P. 1110
Project Name : SUPERTECH CZAR (UPRERAPRJ9414)
District Gautam Buddha Nagar
Promoter Name SUPERTECH LIMITED
Project Category Residential
Sanctioning Competent Greater Noida Authority
Authority
Start Date 15-01-2011
Original Completion Date 30-12-2018
Revised Completion Date
Validity of Sanction Plan 05-03-2018
Total Towers / Blocks 8
Total Units 1484
Completed Towers / Blocks 8
Completed Units 1484
Last Quarterly Progress
Report
Penalty For Not Filing QPR None
Overall Physical Progress (%) 100
Overall Financial Progress 94
(%)
Date of Completion Status Not Available
Certificate
Date of Occupancy Certificate Status Not Available
Complaints by the Allottees 58
Orders (Refund + Possession) Refund- 11, Possession- 27
Click below for more details:
1. Project Registration Details
2.Additional Details Submitted by Promoter
Disclaimer:
The information relating to the projects, given in this report, has been taken from the
details provided by the promoter in the application for registration and subsequent
updates by the promoter on the website of U.P. RERA.
The information has also been taken from the details submitted by the promoter
through the online form provided by the Authority for the purposes of updating the
important details relating to the project in this report.
The Authority has not verified all the information relating to the projects in this
report.