Project Name : VVIP HOMES PH 1 (UPRERAPRJ3390)


         District                              Gautam Buddha Nagar

         Promoter Name                         SOLITAIRE INFRAHOME PRIVATE LIMITED
         Project Category                      Residential

         Sanctioning Competent                 Greater Noida Authority
         Authority
         Start Date                            13-06-2016

         Original Completion Date              13-06-2019
         Revised Completion Date               13-12-2019
         Validity of Sanction Plan             12-06-2021

         Total Towers / Blocks                 8
         Total Units                           1064

         Completed Towers / Blocks             8
         Completed Units                       1064

         Last Quarterly Progress               Jul - Sep 2019
         Report
         Penalty For Not Filing QPR            None

         Overall Physical Progress (%) 100
         Overall Financial Progress            87
         (%)

         Date of Completion                    06-03-2020,06-03-2020,06-03-2020
         Certificate
         Date of Occupancy Certificate

         Complaints by the Allottees           67
         Orders (Refund + Possession) Refund- 7, Possession- 28

         Click below for more details:
         1. Project Registration Details
         2.Additional Details Submitted by Promoter

         Disclaimer:
         The information relating to the projects, given in this report, has been taken from the
         details provided by the promoter in the application for registration and subsequent
         updates by the promoter on the website of U.P. RERA.
             The information has also been taken from the details submitted by the promoter
         through the online form provided by the Authority for the purposes of updating the
         important details relating to the project in this report.
             The Authority has not verified all the information relating to the projects in this

         report.
   1077   1078   1079   1080   1081   1082   1083   1084   1085   1086   1087