Project Name : SHRI RADHA SKY PARK (SKY GARDENS
         PHASE-2) (UPRERAPRJ12851)

         District                              Gautam Buddha Nagar

         Promoter Name                         SJP Infracon Limited
         Project Category                      Residential

         Sanctioning Competent                 Greater Noida Authority
         Authority
         Start Date                            01-11-2017

         Original Completion Date              12-02-2023
         Revised Completion Date               11-08-2023
         Validity of Sanction Plan             20-08-2022

         Total Towers / Blocks
         Total Units

         Completed Towers / Blocks
         Completed Units

         Last Quarterly Progress               Jan - Mar 2020
         Report
         Penalty For Not Filing QPR            None

         Overall Physical Progress (%)
         Overall Financial Progress
         (%)

         Date of Completion                    Work In Progress
         Certificate
         Date of Occupancy Certificate Work In Progress

         Complaints by the Allottees           13
         Orders (Refund + Possession) Refund- 0, Possession- 5

         Click below for more details:
         1. Project Registration Details
         Disclaimer:

         The information relating to the projects, given in this report, has been taken from the
         details provided by the promoter in the application for registration and subsequent
         updates by the promoter on the website of U.P. RERA.
             The information has also been taken from the details submitted by the promoter
         through the online form provided by the Authority for the purposes of updating the
         important details relating to the project in this report.
             The Authority has not verified all the information relating to the projects in this
         report.
   1072   1073   1074   1075   1076   1077   1078   1079   1080   1081   1082