Page 107 - RERA Performance Report 2020
P. 107

Project Name : GANPATI SMART CITY/UNNATI AWAS
         YOJNA PHASE-I (UPRERAPRJ5789)

         District                              Agra

                                               GANPATI INFRASTRUCTURE DEVELOPMENT
         Promoter Name
                                               COMPANY LIMITED
         Project Category                      Residential

         Sanctioning Competent                 Agra Development Authority
         Authority
         Start Date                            01-04-2016

         Original Completion Date              31-03-2021
         Revised Completion Date               30-09-2021

         Validity of Sanction Plan             19-07-2021
         Total Towers / Blocks                 5

         Total Units                           700
         Completed Towers / Blocks             5
         Completed Units                       700

         Last Quarterly Progress
         Report

         Penalty For Not Filing QPR            200000
         Overall Physical Progress (%) 80
         Overall Financial Progress            70
         (%)

         Date of Completion                    Work In Progress
         Certificate

         Date of Occupancy Certificate Work In Progress
         Complaints by the Allottees           2
         Orders (Refund + Possession) Refund- 1, Possession- 0

         Click below for more details:
         1. Project Registration Details
         2.Additional Details Submitted by Promoter

         Disclaimer:
         The information relating to the projects, given in this report, has been taken from the
         details provided by the promoter in the application for registration and subsequent
         updates by the promoter on the website of U.P. RERA.
             The information has also been taken from the details submitted by the promoter
         through the online form provided by the Authority for the purposes of updating the
         important details relating to the project in this report.

             The Authority has not verified all the information relating to the projects in this
         report.