Project Name : G.C. GARDEN TOWNSHIP (UPRERAPRJ13758)
District Agra
Promoter Name G. C. SAHAKARI AWAS SAMITI LIMITED
Project Category Residential
Sanctioning Competent Agra Development Authority
Authority
Start Date 16-01-2015
Original Completion Date 10-01-2023
Revised Completion Date 13-07-2022
Validity of Sanction Plan 01-01-1900
Total Towers / Blocks 1
Total Units 0
Completed Towers / Blocks 0
Completed Units 0
Last Quarterly Progress Apr - Jun 2020
Report
Penalty For Not Filing QPR 100000
Overall Physical Progress (%) 20
Overall Financial Progress 15
(%)
Date of Completion Work In Progress
Certificate
Date of Occupancy Certificate Work In Progress
Complaints by the Allottees 0
Orders (Refund + Possession) Refund- 0, Possession- 0
Click below for more details:
1. Project Registration Details
2.Additional Details Submitted by Promoter
Disclaimer:
The information relating to the projects, given in this report, has been taken from the
details provided by the promoter in the application for registration and subsequent
updates by the promoter on the website of U.P. RERA.
The information has also been taken from the details submitted by the promoter
through the online form provided by the Authority for the purposes of updating the
important details relating to the project in this report.
The Authority has not verified all the information relating to the projects in this
report.