Page 944 - RERA Performance Report 2020
P. 944

Project Name : GREENARCH PHASE-3 (UPRERAPRJ7342)


         District                              Gautam Buddha Nagar

         Promoter Name                         NEW WAY HOMES PRIVATE LIMITED
         Project Category                      Residential

         Sanctioning Competent                 Greater Noida Authority
         Authority
         Start Date                            05-12-2017

         Original Completion Date              05-07-2022
         Revised Completion Date               04-01-2023
         Validity of Sanction Plan             21-05-2020

         Total Towers / Blocks                 2
         Total Units                           336

         Completed Towers / Blocks             0
         Completed Units                       185

         Last Quarterly Progress               Apr - Jun 2020
         Report
         Penalty For Not Filing QPR            None

         Overall Physical Progress (%) 34
         Overall Financial Progress            34
         (%)

         Date of Completion                    Work In Progress
         Certificate
         Date of Occupancy Certificate Work In Progress

         Complaints by the Allottees           0
         Orders (Refund + Possession) Refund- 0, Possession- 0

         Click below for more details:
         1. Project Registration Details
         2.Additional Details Submitted by Promoter

         Disclaimer:
         The information relating to the projects, given in this report, has been taken from the
         details provided by the promoter in the application for registration and subsequent
         updates by the promoter on the website of U.P. RERA.
             The information has also been taken from the details submitted by the promoter
         through the online form provided by the Authority for the purposes of updating the
         important details relating to the project in this report.
             The Authority has not verified all the information relating to the projects in this

         report.