Page 87 - RERA Performance Report 2020
P. 87

Project Name : APARNA PANCHSHEEL (UPRERAPRJ10440)


         District                              Agra

                                               BENARA INFRA STRUCTURE DEVELOPMENT
         Promoter Name
                                               PVT LTD
         Project Category                      Residential

         Sanctioning Competent                 Agra Development Authority
         Authority
         Start Date                            03-07-2013

         Original Completion Date              24-03-2020
         Revised Completion Date

         Validity of Sanction Plan             01-07-2015
         Total Towers / Blocks                 3

         Total Units                           160
         Completed Towers / Blocks             3
         Completed Units                       160

         Last Quarterly Progress               Jan - Mar 2020
         Report

         Penalty For Not Filing QPR            None
         Overall Physical Progress (%) 100
         Overall Financial Progress            100
         (%)

         Date of Completion                    04-07-2020
         Certificate

         Date of Occupancy Certificate
         Complaints by the Allottees           0
         Orders (Refund + Possession) Refund- 0, Possession- 0

         Click below for more details:
         1. Project Registration Details
         2.Additional Details Submitted by Promoter

         Disclaimer:
         The information relating to the projects, given in this report, has been taken from the
         details provided by the promoter in the application for registration and subsequent
         updates by the promoter on the website of U.P. RERA.
             The information has also been taken from the details submitted by the promoter
         through the online form provided by the Authority for the purposes of updating the
         important details relating to the project in this report.

             The Authority has not verified all the information relating to the projects in this
         report.
   82   83   84   85   86   87   88   89   90   91   92