Page 858 - RERA Performance Report 2020
P. 858

Project Name : KVD WINDPARK (UPRERAPRJ3122)


         District                              Gautam Buddha Nagar

         Promoter Name                         KV Developers Private Limited
         Project Category                      Residential

         Sanctioning Competent                 Greater Noida Authority
         Authority
         Start Date                            22-11-2014

         Original Completion Date              07-10-2021
         Revised Completion Date               06-04-2022
         Validity of Sanction Plan             06-10-2021

         Total Towers / Blocks
         Total Units

         Completed Towers / Blocks
         Completed Units

         Last Quarterly Progress               Apr - Jun 2018
         Report
         Penalty For Not Filing QPR            100000

         Overall Physical Progress (%)
         Overall Financial Progress
         (%)

         Date of Completion                    Work In Progress
         Certificate
         Date of Occupancy Certificate Work In Progress

         Complaints by the Allottees           85
         Orders (Refund + Possession) Refund- 19, Possession- 52

         Click below for more details:
         1. Project Registration Details
         Disclaimer:

         The information relating to the projects, given in this report, has been taken from the
         details provided by the promoter in the application for registration and subsequent
         updates by the promoter on the website of U.P. RERA.
             The information has also been taken from the details submitted by the promoter
         through the online form provided by the Authority for the purposes of updating the
         important details relating to the project in this report.
             The Authority has not verified all the information relating to the projects in this
         report.
   853   854   855   856   857   858   859   860   861   862   863