Page 842 - RERA Performance Report 2020
P. 842
Project Name : JKG PALM COURT PHASE-II
(UPRERAPRJ7088)
District Gautam Buddha Nagar
Promoter Name JKG CONSTRUCTION PVT LTD
Project Category Residential
Sanctioning Competent Greater Noida Authority
Authority
Start Date 14-05-2015
Original Completion Date 30-06-2019
Revised Completion Date 09-11-2020
Validity of Sanction Plan 13-05-2020
Total Towers / Blocks 3
Total Units 346
Completed Towers / Blocks 0
Completed Units 0
Last Quarterly Progress Apr - Jun 2020
Report
Penalty For Not Filing QPR 100000
Overall Physical Progress (%) 88
Overall Financial Progress 87
(%)
Date of Completion Status Not Available
Certificate
Date of Occupancy Certificate Status Not Available
Complaints by the Allottees 15
Orders (Refund + Possession) Refund- 6, Possession- 2
Click below for more details:
1. Project Registration Details
2.Additional Details Submitted by Promoter
Disclaimer:
The information relating to the projects, given in this report, has been taken from the
details provided by the promoter in the application for registration and subsequent
updates by the promoter on the website of U.P. RERA.
The information has also been taken from the details submitted by the promoter
through the online form provided by the Authority for the purposes of updating the
important details relating to the project in this report.
The Authority has not verified all the information relating to the projects in this
report.