Project Name : JAYPEE GREENS GREENCREST HOMES,
         SDZ, YEW (UPRERAPRJ5446)

         District                              Gautam Buddha Nagar

         Promoter Name                         Jaiprakash Associates Limited
         Project Category                      Residential

         Sanctioning Competent                 Yamuna Expressway Authority
         Authority
         Start Date                            18-09-2012

         Original Completion Date              31-01-2015
         Revised Completion Date
         Validity of Sanction Plan             10-07-2023

         Total Towers / Blocks                 1
         Total Units                           437

         Completed Towers / Blocks             1
         Completed Units                       437

         Last Quarterly Progress               Jan - Mar 2018
         Report
         Penalty For Not Filing QPR            None

         Overall Physical Progress (%) 100
         Overall Financial Progress            100
         (%)

         Date of Completion                    Status Not Available
         Certificate
         Date of Occupancy Certificate Status Not Available

         Complaints by the Allottees           4
         Orders (Refund + Possession) Refund- 2, Possession- 0

         Click below for more details:
         1. Project Registration Details
         2.Additional Details Submitted by Promoter

         Disclaimer:
         The information relating to the projects, given in this report, has been taken from the
         details provided by the promoter in the application for registration and subsequent
         updates by the promoter on the website of U.P. RERA.
             The information has also been taken from the details submitted by the promoter
         through the online form provided by the Authority for the purposes of updating the
         important details relating to the project in this report.
             The Authority has not verified all the information relating to the projects in this

         report.
   798   799   800   801   802   803   804   805   806   807   808