Project Name : GULSHAN BELLINA (UPRERAPRJ6332)


         District                              Gautam Buddha Nagar

         Promoter Name                         GULSHAN HOMZ PRIVATE LIMITED
         Project Category                      Residential

         Sanctioning Competent                 Greater Noida Authority
         Authority
         Start Date                            03-01-2016

         Original Completion Date              03-01-2022
         Revised Completion Date               02-07-2022
         Validity of Sanction Plan             26-03-2021

         Total Towers / Blocks                 13
         Total Units                           1124

         Completed Towers / Blocks             13
         Completed Units                       1124

         Last Quarterly Progress               Jan - Mar 2020
         Report
         Penalty For Not Filing QPR            None

         Overall Physical Progress (%) 72
         Overall Financial Progress            53
         (%)

         Date of Completion                    Work In Progress
         Certificate
         Date of Occupancy Certificate Work In Progress

         Complaints by the Allottees           2
         Orders (Refund + Possession) Refund- 0, Possession- 0

         Click below for more details:
         1. Project Registration Details
         2.Additional Details Submitted by Promoter

         Disclaimer:
         The information relating to the projects, given in this report, has been taken from the
         details provided by the promoter in the application for registration and subsequent
         updates by the promoter on the website of U.P. RERA.
             The information has also been taken from the details submitted by the promoter
         through the online form provided by the Authority for the purposes of updating the
         important details relating to the project in this report.
             The Authority has not verified all the information relating to the projects in this

         report.
   739   740   741   742   743   744   745   746   747   748   749