Page 698 - RERA Performance Report 2020
P. 698
Project Name : GAUR CITY MALL (UPRERAPRJ6934)
District Gautam Buddha Nagar
Promoter Name Gaursons Hi-Tech Infrastructure Private Limited
Project Category Commercial
Sanctioning Competent Greater Noida Authority
Authority
Start Date 01-09-2014
Original Completion Date 31-12-2023
Revised Completion Date
Validity of Sanction Plan 01-11-2023
Total Towers / Blocks 1
Total Units 0
Completed Towers / Blocks 0
Completed Units 0
Last Quarterly Progress Apr - Jun 2020
Report
Penalty For Not Filing QPR None
Overall Physical Progress (%) 70
Overall Financial Progress 92
(%)
Date of Completion
Certificate
Date of Occupancy Certificate 23-04-2019
Complaints by the Allottees 5
Orders (Refund + Possession) Refund- 2, Possession- 0
Click below for more details:
1. Project Registration Details
2.Additional Details Submitted by Promoter
Disclaimer:
The information relating to the projects, given in this report, has been taken from the
details provided by the promoter in the application for registration and subsequent
updates by the promoter on the website of U.P. RERA.
The information has also been taken from the details submitted by the promoter
through the online form provided by the Authority for the purposes of updating the
important details relating to the project in this report.
The Authority has not verified all the information relating to the projects in this
report.