Page 69 - RERA Performance Report 2020
P. 69
Project Name : ANSAL TOWN AGRA PHASE-III
(UPRERAPRJ3753)
District Agra
Promoter Name Ansal Housing Limited
Project Category Residential
Sanctioning Competent Agra Development Authority
Authority
Start Date 04-04-2016
Original Completion Date 31-12-2019
Revised Completion Date
Validity of Sanction Plan 22-03-2021
Total Towers / Blocks 1
Total Units 528
Completed Towers / Blocks 0
Completed Units 435
Last Quarterly Progress Oct - Dec 2019
Report
Penalty For Not Filing QPR None
Overall Physical Progress (%) 64
Overall Financial Progress 94
(%)
Date of Completion Status Not Available
Certificate
Date of Occupancy Certificate Status Not Available
Complaints by the Allottees 1
Orders (Refund + Possession) Refund- 0, Possession- 0
Click below for more details:
1. Project Registration Details
2.Additional Details Submitted by Promoter
Disclaimer:
The information relating to the projects, given in this report, has been taken from the
details provided by the promoter in the application for registration and subsequent
updates by the promoter on the website of U.P. RERA.
The information has also been taken from the details submitted by the promoter
through the online form provided by the Authority for the purposes of updating the
important details relating to the project in this report.
The Authority has not verified all the information relating to the projects in this
report.