Page 675 - RERA Performance Report 2020
P. 675

Project Name : FUTURE ESTATE (PHASE-FE-1)
         (UPRERAPRJ7361)

         District                              Gautam Buddha Nagar

         Promoter Name                         FUTUREWORLD GREENHOMES PVT. LTD.
         Project Category                      Residential

         Sanctioning Competent                 Greater Noida Authority
         Authority
         Start Date                            10-06-2015

         Original Completion Date              31-12-2018
         Revised Completion Date               29-11-2020
         Validity of Sanction Plan             08-06-2020

         Total Towers / Blocks                 2
         Total Units                           226

         Completed Towers / Blocks             0
         Completed Units                       202

         Last Quarterly Progress               Oct - Dec 2019
         Report
         Penalty For Not Filing QPR            100000

         Overall Physical Progress (%) 76
         Overall Financial Progress            76
         (%)

         Date of Completion                    Status Not Available
         Certificate
         Date of Occupancy Certificate Status Not Available

         Complaints by the Allottees           14
         Orders (Refund + Possession) Refund- 4, Possession- 3

         Click below for more details:
         1. Project Registration Details
         2.Additional Details Submitted by Promoter

         Disclaimer:
         The information relating to the projects, given in this report, has been taken from the
         details provided by the promoter in the application for registration and subsequent
         updates by the promoter on the website of U.P. RERA.
             The information has also been taken from the details submitted by the promoter
         through the online form provided by the Authority for the purposes of updating the
         important details relating to the project in this report.
             The Authority has not verified all the information relating to the projects in this

         report.
   670   671   672   673   674   675   676   677   678   679   680