Project Name : CORPORATE PARK (UPRERAPRJ10013)


         District                              Agra

                                               AGRA INFRALAND DEVELOPERS PRIVATE
         Promoter Name
                                               LIMITED
         Project Category                      Commercial

         Sanctioning Competent                 Agra Development Authority
         Authority
         Start Date                            01-03-2014

         Original Completion Date              30-06-2018
         Revised Completion Date

         Validity of Sanction Plan             26-09-2019
         Total Towers / Blocks                 12

         Total Units                           151
         Completed Towers / Blocks             12
         Completed Units                       151

         Last Quarterly Progress               Oct - Dec 2018
         Report

         Penalty For Not Filing QPR            None
         Overall Physical Progress (%) 100
         Overall Financial Progress            98
         (%)

         Date of Completion                    Status Not Available
         Certificate

         Date of Occupancy Certificate Status Not Available
         Complaints by the Allottees           0
         Orders (Refund + Possession) Refund- 0, Possession- 0

         Click below for more details:
         1. Project Registration Details
         2.Additional Details Submitted by Promoter

         Disclaimer:
         The information relating to the projects, given in this report, has been taken from the
         details provided by the promoter in the application for registration and subsequent
         updates by the promoter on the website of U.P. RERA.
             The information has also been taken from the details submitted by the promoter
         through the online form provided by the Authority for the purposes of updating the
         important details relating to the project in this report.

             The Authority has not verified all the information relating to the projects in this
         report.
   57   58   59   60   61   62   63   64   65   66   67