Project Name : CORPORATE PARK (UPRERAPRJ10013)
District Agra
AGRA INFRALAND DEVELOPERS PRIVATE
Promoter Name
LIMITED
Project Category Commercial
Sanctioning Competent Agra Development Authority
Authority
Start Date 01-03-2014
Original Completion Date 30-06-2018
Revised Completion Date
Validity of Sanction Plan 26-09-2019
Total Towers / Blocks 12
Total Units 151
Completed Towers / Blocks 12
Completed Units 151
Last Quarterly Progress Oct - Dec 2018
Report
Penalty For Not Filing QPR None
Overall Physical Progress (%) 100
Overall Financial Progress 98
(%)
Date of Completion Status Not Available
Certificate
Date of Occupancy Certificate Status Not Available
Complaints by the Allottees 0
Orders (Refund + Possession) Refund- 0, Possession- 0
Click below for more details:
1. Project Registration Details
2.Additional Details Submitted by Promoter
Disclaimer:
The information relating to the projects, given in this report, has been taken from the
details provided by the promoter in the application for registration and subsequent
updates by the promoter on the website of U.P. RERA.
The information has also been taken from the details submitted by the promoter
through the online form provided by the Authority for the purposes of updating the
important details relating to the project in this report.
The Authority has not verified all the information relating to the projects in this
report.