Page 595 - RERA Performance Report 2020
P. 595
Project Name : CAPITAL CITY (UPRERAPRJ7063)
District Gautam Buddha Nagar
Promoter Name BPTP LIMITED
Project Category Commercial
Sanctioning Competent Noida Authority
Authority
Start Date 01-01-2017
Original Completion Date 30-06-2020
Revised Completion Date 29-12-2020
Validity of Sanction Plan 12-03-2017
Total Towers / Blocks 1
Total Units 133
Completed Towers / Blocks 1
Completed Units 133
Last Quarterly Progress Apr - Jun 2020
Report
Penalty For Not Filing QPR None
Overall Physical Progress (%) 100
Overall Financial Progress 84
(%)
Date of Completion Work In Progress
Certificate
Date of Occupancy Certificate Work In Progress
Complaints by the Allottees 8
Orders (Refund + Possession) Refund- 2, Possession- 3
Click below for more details:
1. Project Registration Details
2.Additional Details Submitted by Promoter
Disclaimer:
The information relating to the projects, given in this report, has been taken from the
details provided by the promoter in the application for registration and subsequent
updates by the promoter on the website of U.P. RERA.
The information has also been taken from the details submitted by the promoter
through the online form provided by the Authority for the purposes of updating the
important details relating to the project in this report.
The Authority has not verified all the information relating to the projects in this
report.