Project Name : URBAINIA TRINITY NX (PHASE III)
         (UPRERAPRJ6307)

         District                              Gautam Buddha Nagar

         Promoter Name                         Avdesh Infotech Pvt Ltd/Urbainia Spaces Pvt. Ltd.
         Project Category                      Commercial

         Sanctioning Competent                 Greater Noida Authority
         Authority
         Start Date                            03-01-2016

         Original Completion Date              21-12-2024
         Revised Completion Date               08-04-2023
         Validity of Sanction Plan             09-11-2020

         Total Towers / Blocks                 3
         Total Units                           306

         Completed Towers / Blocks             0
         Completed Units                       0

         Last Quarterly Progress               Apr - Jun 2020
         Report
         Penalty For Not Filing QPR            200000

         Overall Physical Progress (%) 0
         Overall Financial Progress            3
         (%)

         Date of Completion                    Work In Progress
         Certificate
         Date of Occupancy Certificate Work In Progress

         Complaints by the Allottees           0
         Orders (Refund + Possession) Refund- 0, Possession- 0

         Click below for more details:
         1. Project Registration Details
         2.Additional Details Submitted by Promoter

         Disclaimer:
         The information relating to the projects, given in this report, has been taken from the
         details provided by the promoter in the application for registration and subsequent
         updates by the promoter on the website of U.P. RERA.
             The information has also been taken from the details submitted by the promoter
         through the online form provided by the Authority for the purposes of updating the
         important details relating to the project in this report.
             The Authority has not verified all the information relating to the projects in this

         report.
   572   573   574   575   576   577   578   579   580   581   582