Project Name : GH-08/75 (PHASE-1) GOLF CITY
         (UPRERAPRJ11463)

         District                              Gautam Buddha Nagar

         Promoter Name                         Aims Max Gardenia Developers Private Limited
         Project Category                      Residential

         Sanctioning Competent                 Noida Authority
         Authority
         Start Date                            05-03-2012

         Original Completion Date              05-03-2020
         Revised Completion Date
         Validity of Sanction Plan             03-11-2012

         Total Towers / Blocks                 5
         Total Units                           420

         Completed Towers / Blocks             0
         Completed Units                       266

         Last Quarterly Progress               Jan - Mar 2020
         Report
         Penalty For Not Filing QPR            None

         Overall Physical Progress (%) 81
         Overall Financial Progress            68
         (%)

         Date of Completion                    Status Not Available
         Certificate
         Date of Occupancy Certificate Status Not Available

         Complaints by the Allottees           7
         Orders (Refund + Possession) Refund- 0, Possession- 4

         Click below for more details:
         1. Project Registration Details
         2.Additional Details Submitted by Promoter

         Disclaimer:
         The information relating to the projects, given in this report, has been taken from the
         details provided by the promoter in the application for registration and subsequent
         updates by the promoter on the website of U.P. RERA.
             The information has also been taken from the details submitted by the promoter
         through the online form provided by the Authority for the purposes of updating the
         important details relating to the project in this report.
             The Authority has not verified all the information relating to the projects in this

         report.
   491   492   493   494   495   496   497   498   499   500   501