Page 431 - RERA Performance Report 2020
P. 431

Project Name : CONSTRUCTION OF 160 EWS HOUSES AT
         GRAM PANCHAYAT RAMPURA,BULANDSHAHR UNDER

         PMAY (URBAN) (UPRERAPRJ780870)

         District                              Bulandshahr
         Promoter Name                         BULANDSHAHR DEVELOPMENT AUTHORITY

         Project Category                      Residential
         Sanctioning Competent                 Bulandsahar Development Author
         Authority

         Start Date                            01-03-2019
         Original Completion Date              30-06-2020

         Revised Completion Date               29-12-2020
         Validity of Sanction Plan             29-12-2020

         Total Towers / Blocks                 2
         Total Units                           160
         Completed Towers / Blocks             0

         Completed Units                       144
         Last Quarterly Progress               Apr - Jun 2020
         Report

         Penalty For Not Filing QPR            None
         Overall Physical Progress (%) 90

         Overall Financial Progress            70
         (%)
         Date of Completion                    Work In Progress

         Certificate
         Date of Occupancy Certificate Work In Progress
         Complaints by the Allottees           0

         Orders (Refund + Possession) Refund- 0, Possession- 0
         Click below for more details:
         1. Project Registration Details

         2.Additional Details Submitted by Promoter
         Disclaimer:
         The information relating to the projects, given in this report, has been taken from the
         details provided by the promoter in the application for registration and subsequent
         updates by the promoter on the website of U.P. RERA.

             The information has also been taken from the details submitted by the promoter
         through the online form provided by the Authority for the purposes of updating the
         important details relating to the project in this report.
             The Authority has not verified all the information relating to the projects in this
         report.
   426   427   428   429   430   431   432   433   434   435   436