Project Name : PARK AVENUE RESIDENCY ( APARTMENTS )
         (UPRERAPRJ6683)

         District                              Bareilly

         Promoter Name                         D. G. INFRA TOWERS PVT. LTD.
         Project Category                      Residential

         Sanctioning Competent                 Bareily Development Authority
         Authority
         Start Date                            31-03-2015

         Original Completion Date              30-03-2020
         Revised Completion Date               29-09-2020
         Validity of Sanction Plan             30-03-2022

         Total Towers / Blocks                 35
         Total Units                           446

         Completed Towers / Blocks             13
         Completed Units                       152

         Last Quarterly Progress               Apr - Jun 2020
         Report
         Penalty For Not Filing QPR            100000

         Overall Physical Progress (%) 40
         Overall Financial Progress            40
         (%)

         Date of Completion                    Status Not Available
         Certificate
         Date of Occupancy Certificate Status Not Available

         Complaints by the Allottees           0
         Orders (Refund + Possession) Refund- 0, Possession- 0

         Click below for more details:
         1. Project Registration Details
         2.Additional Details Submitted by Promoter

         Disclaimer:
         The information relating to the projects, given in this report, has been taken from the
         details provided by the promoter in the application for registration and subsequent
         updates by the promoter on the website of U.P. RERA.
             The information has also been taken from the details submitted by the promoter
         through the online form provided by the Authority for the purposes of updating the
         important details relating to the project in this report.
             The Authority has not verified all the information relating to the projects in this

         report.
   385   386   387   388   389   390   391   392   393   394   395