Project Name : LIBERTY ENCLAVE (UPRERAPRJ14317)
District Barabanki
Promoter Name GOLDMARK INFRAESTATE PRIVATE LIMITED
Project Category Residential
Sanctioning Competent
Authority
Start Date 28-10-2016
Original Completion Date 27-09-2019
Revised Completion Date
Validity of Sanction Plan
Total Towers / Blocks
Total Units
Completed Towers / Blocks
Completed Units
Last Quarterly Progress
Report
Penalty For Not Filing QPR 200000
Overall Physical Progress (%)
Overall Financial Progress
(%)
Date of Completion Status Not Available
Certificate
Date of Occupancy Certificate Status Not Available
Complaints by the Allottees 0
Orders (Refund + Possession) Refund- 0, Possession- 0
Click below for more details:
1. Project Registration Details
Disclaimer:
The information relating to the projects, given in this report, has been taken from the
details provided by the promoter in the application for registration and subsequent
updates by the promoter on the website of U.P. RERA.
The information has also been taken from the details submitted by the promoter
through the online form provided by the Authority for the purposes of updating the
important details relating to the project in this report.
The Authority has not verified all the information relating to the projects in this
report.