Page 316 - RERA Performance Report 2020
P. 316
Project Name : VINAYAK CENTRAL PARK @ SHERVANI
LEGACY PHASE-2 (UPRERAPRJ421675)
District Allahabaad
Promoter Name Vinayakkripa Homebuild LLP
Project Category Residential
Sanctioning Competent Allahabad Development Authorit
Authority
Start Date 01-11-2019
Original Completion Date 31-12-2026
Revised Completion Date 30-06-2027
Validity of Sanction Plan 20-02-2024
Total Towers / Blocks 3
Total Units 664
Completed Towers / Blocks 0
Completed Units 0
Last Quarterly Progress Apr - Jun 2020
Report
Penalty For Not Filing QPR None
Overall Physical Progress (%) 3
Overall Financial Progress 29
(%)
Date of Completion Work In Progress
Certificate
Date of Occupancy Certificate Work In Progress
Complaints by the Allottees 0
Orders (Refund + Possession) Refund- 0, Possession- 0
Click below for more details:
1. Project Registration Details
2.Additional Details Submitted by Promoter
Disclaimer:
The information relating to the projects, given in this report, has been taken from the
details provided by the promoter in the application for registration and subsequent
updates by the promoter on the website of U.P. RERA.
The information has also been taken from the details submitted by the promoter
through the online form provided by the Authority for the purposes of updating the
important details relating to the project in this report.
The Authority has not verified all the information relating to the projects in this
report.