Project Name : JAYPEE GREENS UDAAN & BOULEVARD
         COURT, MIRZAPUR (UPRERAPRJ4921)

         District                        Gautam Buddha Nagar

         Promoter Name                   Jaypee Infratech Limited
         Project Category                Residential

         Sanctioning Competent           Yamuna Expressway Authority
         Authority
         Start Date                      12-10-2013

         Original Completion Date 30-06-2022
         Revised Completion Date 29-12-2022
         Validity of Sanction Plan 06-02-2019

         Total Towers / Blocks
         Total Units

         Completed Towers /
         Blocks
         Completed Units

         Last Quarterly Progress
         Report

         Penalty For Not Filing          200000
         QPR
         Overall Physical Progress
         (%)

         Overall Financial
         Progress (%)
         Date of Completion              Work In Progress
         Certificate

         Date of Occupancy               Work In Progress
         Certificate
         Complaints by the               3

         Allottees
         Orders (Refund +                Refund- 0, Possession- 0
         Possession)

         Click below for more details:
         1. Project Registration Details
         Disclaimer:
         The information relating to the projects, given in this report, has been taken from the
         details provided by the promoter in the application for registration and subsequent

         updates by the promoter on the website of U.P. RERA.
             The information has also been taken from the details submitted by the promoter
         through the online form provided by the Authority for the purposes of updating the
         important details relating to the project in this report.
             The Authority has not verified all the information relating to the projects in this

         report.
   2867   2868   2869   2870   2871   2872   2873   2874   2875   2876   2877