Project Name : UDHYAM VATIKA (UPRERAPRJ6692)
District Varanasi
REWARDING INFRADEVELOPER PRIVATE
Promoter Name
LIMITED
Project Category Residential
Sanctioning Competent Varanasi Development Authority
Authority
Start Date 17-08-2017
Original Completion Date 18-08-2023
Revised Completion Date 17-02-2024
Validity of Sanction Plan 27-02-2023
Total Towers / Blocks
Total Units
Completed Towers / Blocks
Completed Units
Last Quarterly Progress Oct - Dec 2019
Report
Penalty For Not Filing QPR 100000
Overall Physical Progress (%)
Overall Financial Progress
(%)
Date of Completion Work In Progress
Certificate
Date of Occupancy Certificate Work In Progress
Complaints by the Allottees 0
Orders (Refund + Possession) Refund- 0, Possession- 0
Click below for more details:
1. Project Registration Details
Disclaimer:
The information relating to the projects, given in this report, has been taken from the
details provided by the promoter in the application for registration and subsequent
updates by the promoter on the website of U.P. RERA.
The information has also been taken from the details submitted by the promoter
through the online form provided by the Authority for the purposes of updating the
important details relating to the project in this report.
The Authority has not verified all the information relating to the projects in this
report.