Page 2702 - RERA Performance Report 2020
P. 2702

Project Name : SAMPADA RESIDENCY (UPRERAPRJ318260)


         District                              Varanasi

         Promoter Name                         PRIME BUILDERS AND DEVELOPERS
         Project Category                      Residential

         Sanctioning Competent                 Varanasi Development Authority
         Authority
         Start Date                            15-01-2019

         Original Completion Date              14-01-2022
         Revised Completion Date               30-09-2022
         Validity of Sanction Plan             03-10-2021

         Total Towers / Blocks                 1
         Total Units                           78

         Completed Towers / Blocks             0
         Completed Units                       42

         Last Quarterly Progress               Jan - Mar 2020
         Report
         Penalty For Not Filing QPR            100000

         Overall Physical Progress (%) 60
         Overall Financial Progress            53
         (%)

         Date of Completion                    Work In Progress
         Certificate
         Date of Occupancy Certificate Work In Progress

         Complaints by the Allottees           0
         Orders (Refund + Possession) Refund- 0, Possession- 0

         Click below for more details:
         1. Project Registration Details
         2.Additional Details Submitted by Promoter

         Disclaimer:
         The information relating to the projects, given in this report, has been taken from the
         details provided by the promoter in the application for registration and subsequent
         updates by the promoter on the website of U.P. RERA.
             The information has also been taken from the details submitted by the promoter
         through the online form provided by the Authority for the purposes of updating the
         important details relating to the project in this report.
             The Authority has not verified all the information relating to the projects in this

         report.
   2697   2698   2699   2700   2701   2702   2703   2704   2705   2706   2707