Project Name : CHANDRA ANANDAM (UPRERAPRJ248919)


         District                              Varanasi

         Promoter Name                         CHANDRA TOWER PVT LTD
         Project Category                      Residential

         Sanctioning Competent                 Varanasi Development Authority
         Authority
         Start Date                            11-02-2019

         Original Completion Date              11-02-2024
         Revised Completion Date               10-08-2024
         Validity of Sanction Plan             11-02-2024

         Total Towers / Blocks
         Total Units

         Completed Towers / Blocks
         Completed Units

         Last Quarterly Progress               Apr - Jun 2020
         Report
         Penalty For Not Filing QPR            None

         Overall Physical Progress (%)
         Overall Financial Progress
         (%)

         Date of Completion                    Work In Progress
         Certificate
         Date of Occupancy Certificate Work In Progress

         Complaints by the Allottees           0
         Orders (Refund + Possession) Refund- 0, Possession- 0

         Click below for more details:
         1. Project Registration Details
         Disclaimer:

         The information relating to the projects, given in this report, has been taken from the
         details provided by the promoter in the application for registration and subsequent
         updates by the promoter on the website of U.P. RERA.
             The information has also been taken from the details submitted by the promoter
         through the online form provided by the Authority for the purposes of updating the
         important details relating to the project in this report.
             The Authority has not verified all the information relating to the projects in this
         report.
   2662   2663   2664   2665   2666   2667   2668   2669   2670   2671   2672