Page 255 - RERA Performance Report 2020
P. 255
Project Name : SUNSHINE ROYAL PALACE
(UPRERAPRJ6445)
District Allahabaad
Promoter Name HK INFRAVENTURES PRIVATE LIMITED
Project Category Residential
Sanctioning Competent Allahabad Development Authorit
Authority
Start Date 01-02-2015
Original Completion Date 30-06-2018
Revised Completion Date
Validity of Sanction Plan 20-10-2019
Total Towers / Blocks 1
Total Units 52
Completed Towers / Blocks 1
Completed Units 52
Last Quarterly Progress Jan - Mar 2019
Report
Penalty For Not Filing QPR None
Overall Physical Progress (%) 100
Overall Financial Progress 100
(%)
Date of Completion 11-03-2019
Certificate
Date of Occupancy Certificate
Complaints by the Allottees 0
Orders (Refund + Possession) Refund- 0, Possession- 0
Click below for more details:
1. Project Registration Details
2.Additional Details Submitted by Promoter
Disclaimer:
The information relating to the projects, given in this report, has been taken from the
details provided by the promoter in the application for registration and subsequent
updates by the promoter on the website of U.P. RERA.
The information has also been taken from the details submitted by the promoter
through the online form provided by the Authority for the purposes of updating the
important details relating to the project in this report.
The Authority has not verified all the information relating to the projects in this
report.