Page 2535 - RERA Performance Report 2020
P. 2535

Project Name : BHAGIRATHI ENCLAVE F-32 TYPE 384 NOS
         (G+3) HOUSES (UPRERAPRJ9757)

         District                              Meerut

         Promoter Name                         U.P. Awas Evam Vikas Parishad
         Project Category                      Residential

         Sanctioning Competent                 U.P. Awas Evam Vikas Parishad
         Authority
         Start Date                            17-01-2014

         Original Completion Date              31-12-2017
         Revised Completion Date
         Validity of Sanction Plan             13-11-2018

         Total Towers / Blocks                 24
         Total Units                           384

         Completed Towers / Blocks             24
         Completed Units                       384

         Last Quarterly Progress               Jan - Mar 2018
         Report
         Penalty For Not Filing QPR            None

         Overall Physical Progress (%) 100
         Overall Financial Progress            100
         (%)

         Date of Completion                    13-03-2019
         Certificate
         Date of Occupancy Certificate

         Complaints by the Allottees           1
         Orders (Refund + Possession) Refund- 0, Possession- 0

         Click below for more details:
         1. Project Registration Details
         2.Additional Details Submitted by Promoter

         Disclaimer:
         The information relating to the projects, given in this report, has been taken from the
         details provided by the promoter in the application for registration and subsequent
         updates by the promoter on the website of U.P. RERA.
             The information has also been taken from the details submitted by the promoter
         through the online form provided by the Authority for the purposes of updating the
         important details relating to the project in this report.
             The Authority has not verified all the information relating to the projects in this

         report.
   2530   2531   2532   2533   2534   2535   2536   2537   2538   2539   2540