Project Name : APEX ENCLAVE (UPRERAPRJ745920)


         District                              Meerut

         Promoter Name                         SHREE AADINATH ESTATE DEVELOPERS
         Project Category                      Residential

         Sanctioning Competent                 Meerut Development Authority
         Authority
         Start Date                            22-02-2020

         Original Completion Date              22-10-2024
         Revised Completion Date               21-04-2025
         Validity of Sanction Plan             22-10-2024

         Total Towers / Blocks                 2
         Total Units                           101

         Completed Towers / Blocks             0
         Completed Units                       101

         Last Quarterly Progress               Apr - Jun 2020
         Report
         Penalty For Not Filing QPR            None

         Overall Physical Progress (%) 60
         Overall Financial Progress            60
         (%)

         Date of Completion                    Work In Progress
         Certificate
         Date of Occupancy Certificate Work In Progress

         Complaints by the Allottees           0
         Orders (Refund + Possession) Refund- 0, Possession- 0

         Click below for more details:
         1. Project Registration Details
         2.Additional Details Submitted by Promoter

         Disclaimer:
         The information relating to the projects, given in this report, has been taken from the
         details provided by the promoter in the application for registration and subsequent
         updates by the promoter on the website of U.P. RERA.
             The information has also been taken from the details submitted by the promoter
         through the online form provided by the Authority for the purposes of updating the
         important details relating to the project in this report.
             The Authority has not verified all the information relating to the projects in this

         report.
   2515   2516   2517   2518   2519   2520   2521   2522   2523   2524   2525