Project Name : SHRI SAI UPVAN (UPRERAPRJ6327)


         District                              Meerut

         Promoter Name                         ISHA DEVELOPERS & BUILDERS PVT LTD
         Project Category                      Residential

         Sanctioning Competent                 Meerut Development Authority
         Authority
         Start Date                            05-10-2015

         Original Completion Date              04-10-2023
         Revised Completion Date               01-04-2024
         Validity of Sanction Plan             02-09-2023

         Total Towers / Blocks                 1
         Total Units                           100

         Completed Towers / Blocks             1
         Completed Units                       32

         Last Quarterly Progress               Jul - Sep 2019
         Report
         Penalty For Not Filing QPR            200000

         Overall Physical Progress (%) 100
         Overall Financial Progress            85
         (%)

         Date of Completion                    Work In Progress
         Certificate
         Date of Occupancy Certificate Work In Progress

         Complaints by the Allottees           0
         Orders (Refund + Possession) Refund- 0, Possession- 0

         Click below for more details:
         1. Project Registration Details
         2.Additional Details Submitted by Promoter

         Disclaimer:
         The information relating to the projects, given in this report, has been taken from the
         details provided by the promoter in the application for registration and subsequent
         updates by the promoter on the website of U.P. RERA.
             The information has also been taken from the details submitted by the promoter
         through the online form provided by the Authority for the purposes of updating the
         important details relating to the project in this report.
             The Authority has not verified all the information relating to the projects in this

         report.
   2475   2476   2477   2478   2479   2480   2481   2482   2483   2484   2485